MVEC "NAMED"

Деривационна ВЕЦ е разположена на р. Чепеларска, с водохващане в с. Named.

Project Manager: Yuzina B.B. Ltd
Responsibilities of Hydrosis Engineering Ltd: Design of parts Hydraulics, Hydrotechnical, Constructive of HTS, Plumbing, PB, PBZ
Location: with. Named, common. Asenovgrad
Status: Built, in operation

Technical parameters

Gross effort: 23,67m
Built-up water quantity: 5,5m³/s
Total power: 870kW
Turbine type: 1бр Crossflow турбина